The International Energy Conservation Code (IECC) is a building code created by the International Code Council in 2000. It is a model code adopted by many states and local governments in the United States for the establishment of minimum design and construction requirements for energy efficiency.

In 2012, the IECC published air barrier requirements, which states, "Continuous air barrier shall be provided throughout the building envelope with the exception of climate zones 1, 2, and 3." The purpose of an air barrier is straightforward:

  • Minimize the loss of conditioned air from within a building
  • Reduce energy loss — increase building energy efficiency

So, what does this mean for the commercial low-slope roof? Most people would assume that low-slope roof membranes are air barriers. However, that's not the case and it's very important to note that:

  • The air barrier is the system of materials that controls air leakage/convective heat flow through the building enclosure
  • The air barrier is not one material but instead is an integrated system of many different materials/components

Roofing membranes generally are very good at blocking airflow, but unless they are properly tied into the other parts of the building envelope, the building will still leak air. There are three ways of achieving compliance with air barrier requirements:

  • Materials (i.e. prescriptive) – the IECC published a list of materials they consider to be air barriers when installed the right way. Materials not on the list must be tested and shown to have an air permeance ≤ 0.004 cfm/ft2 under pressure differential of 0.3 in. water tested in accordance with ASTM E 2178.
  • Assemblies – assemblies of materials and components (sealants, tapes, etc.) that are to be used can be built and then tested. An average air permeance ≤ 0.04 cfm/ft2 under pressure differential of 0.3 in. w.g. tested in accordance with ASTM E 2357, 1677, or 283 is required.
  • Whole building testing – air leakage rate of completed building can be tested and confirmed to be ≤ 0.40 cfm/ft2 at a pressure differential of 0.3 inches water per ASTM E779 or equivalent method approved by a code official.

The IECC published a list of what are automatically considered to be air barriers. This is shown here:

  • Fully adhered roof systems, single ply, BUR, mod. bit.
  • Min. 3/8" plywood with taped, sealed joints
  • Min. 3/8" OSB with taped, sealed joints
  • Min. ½" extruded polystyrene with sealed joints
  • Foil-backed polyiso min. ½" thickness with sealed joints
  • Closed-cell SPF min. 1.5" and min. 1.5 pcf density
  • Open-cell SPF min. 0.4 – 1.5 pcf and min. 4.5" thickness
  • Min. ½" exterior or interior gypsum or cement board with sealed joints
  • Pre-cast or cast-in-place concrete
  • Fully grouted concrete block masonry with paint coating or sealer
  • Sheet steel or aluminum

The American Society of Heating, Refrigerating & Air Conditioning Engineers regularly update the ASHRAE 90.1 standard that provides minimum requirements for energy–efficient designs for buildings except for low-rise residential buildings. They have included many of the IECC code requirements, but removed the words "fully adhered" from the roof system requirements.

Both ASHRAE and NRCA are working to get the "fully adhered" requirement removed from the IECC. However, mechanically attached systems can still be used provided that the final system complies with air-barrier requirements. That means either testing of a representative assembly or whole building testing after construction.

While the IECC is a model code and ASHRAE 90.1 is a standard, their respective requirements do get adopted into energy and building codes. Also, ASHRAE 90.1 is an industry standard referenced in the LEED® building certification program. It is frequently used as a baseline for comparison during energy retrofit projects or any project that employs building energy simulation.

As IECC and ASHRAE 90.1 get adopted and even surpassed, we can expect more attention to be focused on exactly how low-slope roofing membranes interface with air barriers within wall systems. It's important to remember that air barriers are the system, not individual materials. Building design professionals have an important role to play in helping to ensure compliance with these toughening regulations.

Don't miss another GAF RoofViews post!
LATEST UPDATES
A typical PVC roofing system will consist of insulation board and membrane over the structural deck. As with other single-ply roofing systems, there are multiple ways to fasten the PVC roofing membrane.
Volunteerism rates have steadily increased in recent years, and employees are looking for more opportunities to put their skills to work and perhaps even learn new skills along the way. One organization that often encourages a bit of both is Habitat for Humanity, where volunteers build homes for families in need across the U.S.
Taking care of your health and your home are two of the most important ways to support ourselves and our families. Amparo Sancen understands this—and she excels at helping others do just that. She grew up in Mexico watching her mom, who struggled with health issues, navigate medical appointments and doctor visits. This early exposure to the sometimes complicated medical world inspired Amparo to find a career that would allow her to help others. Healthcare was a natural fit, driving her to take a first-aid course when she was 13 years old. Once out of school, Amparo began studying nursing but then moved to Atlanta before she could complete those studies. There, she began working as a nursing assistant—until she learned more about the roofing industry, that is.
Taking on a new roofing project means collecting plenty of information before you even consider stepping foot in a roofing supply store. The key is to ask the right questions—and know how to find the answers you need.
In 2011, employees at the GAF Chester plant in Rock Hill, South Carolina had an idea to reduce waste being generated by the manufacturing facility. The initial idea has grown into a model of collaboration and innovation: reusing cardboard mat cores.
Introduction Wind design of roof systems can be confusing from an engineering perspective. Wind design can also be confusing because the International Building Code (IBC) provides specific requirements, but so does Factory Mutual (FM). If FM is specified, do the IBC requirements need to be followed? What is the wind-design strategy for FM-insured and non-FM-insured buildings? This blog will discuss the following:
This blog contains information created by a variety of sources, including internal and third party writers. The opinions and views expressed do not necessarily represent those of GAF. The content is for informational purposes only. It is not intended to constitute financial, accounting, tax or legal advice. GAF does not guarantee the accuracy, reliability, and completeness of the information. In no event shall GAF be held responsible or liable for errors or omissions in the content or for the results, damages or losses caused by or in connection with the use of or reliance on the content.

Interested in sharing or republishing our content? We kindly ask you to adhere to our guidelines.